A 90-second power outage at the Manchester signaling center stranded trains across northwest England and Wales; recovery continues through Friday afternoon.
Rail passengers in England faced a second day of delays Friday after a 90-second power cut at a signaling control center in Manchester brought trains to a standstill across the northwest and the Midlands, reaching into Wales.
National Rail said trains were moving again and warned that disruption would persist through Friday afternoon on the West Coast main line and on services run by East Midlands Railway, Northern, TransPennine Express and Transport for Wales. The problem, the rail operator said, is trains and crews sitting out of position after Thursday's shutdown.
"This means that some trains are still expected to be affected this morning," Network Rail, the track operator, said in a statement. "Trains across the Greater Manchester area and northwest of England may still be canceled in full or revised to only run for part of their normal journey until service is able to fully recover."
Northern Rail told passengers not to attempt travel before 10 a.m. local time. TransPennine Express said to expect delays and cancellations until midday.
Power briefly cut out at the Manchester Rail Operating Center on Thursday afternoon. An emergency backup supply failed to come online in time, and the entire signaling system went down. The center sits at the heart of a major upgrade begun in 2014 that phased out trackside signal boxes in favor of remote-controlled facilities.
Criticism of years of restrained state funding and large-scale layoffs at Network Rail, which owns the track and signaling infrastructure and cut staff at the start of 2026, sharpened in the aftermath.
Government figures from the Office of Road and Rail for the January to March quarter show nearly 81,000 main-line train services, or 3.2%, were either pulled or partly canceled. The office flagged "severely disrupted days" when at least 5% of services were cancelled. By the same measure, more than 86% of trains arrived ahead of schedule or within three minutes of the timetable.
Network Rail's northwest director, Chris Wright, apologised and said engineers had worked through the night to get signaling back online and trains moving again. "Of course we will be conducting a really thorough investigation to understand what went wrong and how we learn from this in the future," he said. "We need to learn from this. We must do better."
Wright said most services were now operating. National Rail said the recovery would continue through Friday afternoon.
Drafted by a large language model from the source reporting linked above, then screened by automated publishing checks. It is not read by a journalist before publication. Some articles cite our Alpha Score. Verify prices and figures against the original source. Educational coverage, not personalized advice.