
Kenmare posted a $34.1M H1 loss after ilmenite output fell 39% and revenue dropped 16%. The titanium miner said a strengthening zircon market and WCP A progress support H2.
Kenmare Resources posted a $34.1 million loss after tax in the first half of 2026 as weak titanium feedstock markets and slower-than-expected commissioning of its Wet Concentrator Plant A cut ilmenite production by 39% and revenue by 16%.
"Weak market conditions for our products, combined with the slower than expected commissioning of WCP A, continued to impact Kenmare's financial performance in H1 2026," Managing Director Tom Hickey said. "However, with a strengthening zircon market and the capital expenditure for the WCP A upgrade project now substantially complete, the outlook is slightly improved."
Production of heavy mineral concentrate fell 34% year-on-year to 442,200 tonnes. The drop reflected a 26% decrease in excavated ore grades as WCP A reaches the end of its mine path in Namalope, plus a 10% decline in excavated ore volumes due to the commissioning delays and a temporary stoppage of dry mining at WCP B for most of the second quarter. Ilmenite output, the company’s primary product, dropped to 273,100 tonnes. Primary zircon production fell 32% to 18,600 tonnes, while rutile declined 44% to 2,700 tonnes.
Concentrates production jumped 599% to 135,700 tonnes, driven by the conversion of a 102,200-tonne tailings stockpile into ZrTi product to meet customer demand. Kenmare expects to generate 30,000-40,000 tonnes of ZrTi per year going forward.
Production and Operational Challenges
WCP A, Kenmare’s largest mining plant, averaged 2,800 tonnes per hour in H1, well below its design nameplate of 3,500 tph, mainly due to dredging performance. The company is working with suppliers and consultants on testing, spares lead times, and operational techniques. Downstream modifications, including debottlenecking of the desliming circuit, have been implemented. Throughputs and utilisation rates improved in July and early August, the company said.
All major construction and installation work for the WCP A upgrade is now complete. Capital expenditure on the project fell to $23 million in H1, with only $7 million expected in H2. The plant is scheduled to begin its transition to the Nataka ore zone in the second half, which contains about 70% of Moma’s nine billion tonnes of mineral resources.
Kenmare commissioned its first small-scale, low-cost mining operation, SMO 1, in 2025. A second unit, SMO 2, with a capacity of 1,000 tph, is under construction. The first phase at 500 tph is expected to be commissioned in the fourth quarter of 2026 at a cost of $5.3 million. The second phase will follow in 2027.
Financial Performance and Outlook
Mineral product revenue fell 16% to $134.5 million as shipments rose 14% to 555,600 tonnes but the average price received dropped 26% to $242 per tonne. Ilmenite revenue declined 33% to $86.8 million. Zircon revenue rose 18% to $23 million as prices increased during H1 versus H2 2025, reflecting a recovering market.
Total cash operating costs fell 12% to $109.6 million, driven by lower labour and production overheads. EBITDA was $4.4 million, compared with an adjusted $47.2 million in H1 2025. No impairment was recognised after the company’s impairment review showed the Moma mine’s recoverable amount exceeded its carrying value by $67 million, using a 13% discount rate.
Kenmare drew no new debt during the period. In late June it upsized its revolving credit facility to $230 million from $200 million and amended financial covenants to increase flexibility. Net debt stood at $175.8 million at June 30, up from $158.8 million at year-end 2025. Cash and cash equivalents fell to $31 million from $48.6 million. The board suspended dividend payments in March to preserve liquidity.
For the full year, Kenmare expects shipments of at least 1.1 million tonnes, a 15% increase from 2025. Ilmenite production guidance was moderated to approximately 800,000 tonnes, from more than 800,000 tonnes previously. Total cash operating costs are expected to be $215 million to $225 million, 7% to 12% lower than 2025. The company plans to spend about $30 million in capital in H2, with only $7 million on WCP A.
"Kenmare remains on track to achieve its 2026 shipments guidance, which is our key metric for the year," Hickey said. "We expect to achieve our annual operating and capital cost guidance."
Prepared with AlphaScala editorial tooling from the source reporting linked above. Indexable analysis may include a cited Alpha Score value. Publishing checks screen each story before release. Educational coverage, not personalized advice.