Karnataka RERA ordered a builder to deliver promised amenities after a 6-year delay. Homebuyers can file complaints for similar issues under state RERA laws.
A Bengaluru homebuyer who paid ₹40 lakh and took possession of his apartment in February 2017 has been waiting more than six years for basic amenities the builder promised, including Cauvery water, BESCOM electricity meters and DG generator power supply. The complainant from Arasinakunte, Bengaluru rural, approached the Karnataka Real Estate Regulatory Authority (K-RERA) for relief, according to an Economic Times report.
The homebuyer said the builder assured him Cauvery water would be provided for all apartments and even collected a deposit of ₹14,895. Six years later, that promise remained unfulfilled. The builder also promised two separate pipelines for borewell and treated water but failed to install a separate overhead tank for storing Cauvery water.
The builder has not started any process for forming the apartment owners association or transferring common areas to the homeowners, the complainant alleged. He said he suspects the builder may be misappropriating funds, as no audited balance sheet, books of accounts or receipts have been provided since 2017.
The builder disconnected the DG generator backup power supply to his apartment, the complainant said. During BESCOM outages, he faced severe hardship because, as a senior citizen, he depended on the refrigerator to preserve his medicines.
K-RERA partly ruled in the complainant's favor in an order dated June 3, 2026. Citing the Supreme Court's ruling in Newtech Promoters and Developers v. State of Uttar Pradesh, the authority observed that the RERA Act has a retroactive effect, ensuring homebuyers are protected and developers must fulfill promises in the sale agreement.
K-RERA held that providing extra amenities does not absolve the builder's obligations to complete all amenities promised in the prospectus. The authority ruled the complainant is entitled to have the assured amenities completed in a functional condition, along with a refund of the corpus fund.
Homebuyers who face similar issues can approach their state's RERA. The legal route allows complaints against builders who fail to deliver promised amenities such as a club house, gym, swimming pool or park. Homebuyers can also file complaints over delayed possession despite payment, poor construction quality, non-registration of property, or other contract violations.
Every Indian state has its own RERA. While the core law applies nationwide, local authorities frame specific rules and manage dedicated state portals for project registration, builder compliance and dispute resolution.
Drafted by a large language model from the source reporting linked above, then screened by automated publishing checks. It is not read by a journalist before publication. Some articles cite our Alpha Score. Verify prices and figures against the original source. Educational coverage, not personalized advice.