India's power regulator told clean energy firms to surrender unused grid rights or post more collateral, freeing 15.7 GW of capacity for active projects.
India ordered renewable energy companies to either surrender unused transmission rights or post higher bank guarantees, a move meant to free grid capacity for projects that are actually generating power.
The Central Electricity Regulatory Commission, in a July 11 order, said companies can also transfer transmission rights to a group utility that is generating but lacks grid connectivity. The regulator noted that a large volume of renewable capacity awarded between 2019 and 2025 has no customers yet.
About 15.7 gigawatts of transmission connectivity is tied up by projects that may never move ahead, the CERC said. That capacity could be released for other developers.
Power producers that want to keep their transmission rights must provide additional bank guarantees and develop the project independently, the order said. Connectivity that is surrendered will first go to existing applicants in the same substation cluster. Any remaining capacity will be auctioned.
Drafted by a large language model from the source reporting linked above, then screened by automated publishing checks. It is not read by a journalist before publication. Some articles cite our Alpha Score. Verify prices and figures against the original source. Educational coverage, not personalized advice.