Bass Oil output rose 3% in June to 225 bopd as the Bunian 6 well started drilling. The Vanessa gas field acquisition closed mid-month, with first sales targeted by year-end.
Bass Oil (ASX: BAS) lifted June output 3% from May to 225 barrels of oil per day, with the Bunian 6 development well now drilling and expected online by late August. The company said it is targeting a doubling of group production once the well comes on stream.
Net sales revenue hit A$561,477 for the month. Bass produced 2,527 barrels from the Cooper Basin and 4,219 barrels net from its Indonesian operations, where the Tangai-Sukananti Oil fields averaged 141 bopd, up 2%. Indonesian barrels sold at an average US$77.48 each.
Cooper Basin output averaged 84 bopd, up 4% from May. The Worrior and Padulla facilities ran at 99% and 96% uptime respectively. Bass sold 1,114 Cooper Basin barrels at an average A$116.58 per barrel. Rain had closed roads to trucking, which the company expects to resume in late July.
Bunian 6 started drilling on 5 June. The well is part of Bass's Indonesian development program. The company did not specify the well's expected initial flow rate.
Bass completed the acquisition of the 100%-owned Vanessa gas field and associated facility in mid-June. The deal added a processing plant and a 5-kilometre pipeline connected to the Cooper Basin gas network. GPA Engineering is defining the scope to recommission the facility, with first gas sales into the east coast market estimated by year-end.
The Vanessa acquisition gives Bass a chance to book remaining conventional gas reserves and assess untested conventional and tight gas potential in the Toolachee and Patchawarra formations through the existing well. The well also penetrated the full Permian sedimentary sequence, offering a location to test deep coal potential within the surrounding permit area.
GPA Engineering is also updating early engineering work for the 100%-owned Kiwi 1 Field Development. Bass is discussing potential infrastructure connections before selecting a development concept. The company received a 25% advance from the A$3.5 million South Australian government grant intended to accelerate the Kiwi development.
Reprocessing of the Dundinna 3D seismic survey is almost complete. Early mapping of the improved dataset has produced encouraging results, Bass said. The company has sent Kiwi condensate and Arrabury Trough rock samples to a specialist US laboratory to investigate the source of the liquids-rich gas and guide exploration around the field.
Elsewhere in the Cooper Basin, results from a deep coal appraisal program using high-angle or horizontal wells and multi-stage fracture stimulation may inform Bass's own commercialisation plans.