
Naqi Water's SAR 1.2M related-party addendum pushes Riyadh factory start to H1 2027. Expansion adds capacity, but delay and related-party structure raise governance questions.
Naqi Water (2282) signed a SAR 1.2 million addendum to the contract for its new Riyadh factory. The work covers additional civil and electrical installations, including a mezzanine floor for packaging equipment and an upgraded main circuit breaker. The company said the changes are meant to boost production capacity and prepare the plant for future expansion.
The original contract, signed in October 2025 with Al-Maamari Advanced Co., was valued at SAR 16.52 million. The total project cost now stands at roughly SAR 17.7 million. Naqi Water said delivery is expected in the first half of 2027.
The timeline slipped. The company cited delays in supplying project materials for logistical reasons and the extra time needed for the additional works. The original completion date was not disclosed.
The contractor is a related party. A major shareholder in Al-Maamari Advanced Co. owns 50% of its capital. That same shareholder also owns 50% of United Seqa Group, which holds 35% of Naqi Water. The transaction was approved under Naqi Water's related-party procedures, in line with Capital Market Authority rules.
The simple take: Naqi Water is investing in a factory to increase capacity. Companies do this.
The better read: The addendum is small relative to the original contract, about 7%. The contractor is a related entity, and the timeline has already slipped well past the original expectation. The company did not say what the original delivery date was, so the length of the delay is unclear. The additional costs and delays come from extra development works that the company says will strengthen infrastructure and boost production capacity. That framing is standard. The key question is whether these overruns and delays will recur.
Investors should watch for two things. First, whether the total project cost stays within SAR 17.7 million or further addenda appear. Second, what production capacity the factory will add, since that determines the revenue impact. The related-party governance structure adds an extra layer of scrutiny. The major shareholder in the contractor also holds a meaningful indirect stake in Naqi Water through United Seqa Group, creating an obvious conflict on scope and pricing.
The next concrete milestone is H1 2027, when the factory is supposed to be ready. Between now and then, each quarterly report will show whether costs or timelines have changed. If they do, the market will have to weigh whether the expansion story still holds.
Prepared with AlphaScala editorial tooling from the source reporting linked above. Indexable analysis may include a cited Alpha Score value. Publishing checks screen each story before release. Educational coverage, not personalized advice.